Hot weather hinders landing stage removal - Jersey Evening Post

by · Jersey Evening Post

Posted inNews

Hot weather hinders landing stage removal

by James Jeune 14 July 202613 July 2026

Share this:

THE removal of the deteriorating landing stage at the end of Gorey Pier is taking longer than initially expected – partially due to the recent hot weather slowing demolition progress.

The works, which involve the removal of the upper deck and support pillars as well as the installation of temporary support bracing from the lower deck to the original pier structure, started in mid-May.

Ports of Jersey had previously hoped the works would begin in April, “with completion targeted just ahead of the summer holidays”.

In an update sent to harbour users yesterday, Ports project and events support manager Kim Dréan said that – while “good progress” was being made – the programme needed to be extended.

It is now forecast to be completed in the final week of August.

Ms Dréan explained: “The removal of the landing stage is a complex demolition project involving a historic structure in a challenging marine environment.

“The installation of the specialist scaffolding required to safely access and dismantle the structure has taken longer than originally anticipated.”

She continued: “In addition, several minor design refinements were identified once works commenced and have been incorporated into the project to ensure the works continue to be delivered safely and effectively.

“More recently, the period of exceptionally hot weather has also affected site productivity, reducing the safe working hours available and slowing progress.”

However, Ms Dréan contended that such programme adjustments were “not uncommon on projects of this complexity”, particularly where access constraints and site conditions “become clearer” once works are underway.

She added that Ports was working closely with the contractor for the demolition works “to maximise progress, recover time where it is safe and practical to do so, and minimise disruption to pier users”.

“A number of mitigation measures have already been implemented, and the team continues to review opportunities to reduce the impact of the works while maintaining the required safety standards,” she said.

The project forms part of a wider stabilisation strategy intended to ensure Gorey Pier’s long-term structural integrity.

Ms Dréan said: “Our priority remains completing the demolition safely, protecting the integrity of the historic pier structure, and returning the area to normal use as soon as possible.

“We appreciate that these works create disruption and would like to thank pier users, local residents and businesses for their continued patience and cooperation while these essential stabilisation works are carried out.”

Related

Read the latest free supplements

Read the Homelife, Connect and a whole host of other subjects like ranging from cycling to travel.

View all our latest supplements now >