EU’s carbon market: The price signal works, but Member States and the grid must catch up

by · Open Access Government

The EU’s carbon market is working as designed, up to a point. Dr Graeme Hutchison, Grid Consultancy Managing Director at Eclipse Power, argues that Member States must now close the gap between climate finance and delivery

Capital and construction operate on different timelines. Capital can be deployed incredibly fast, while planning and building an overhead transmission line takes around 15 years. That’s the fundamental mismatch at the heart of Europe’s climate challenge. Money and incentives to act are moving faster than the ability to deploy the infrastructure needed for a lower-emission, electrified economy.

So, despite the funds raised by the European Union (EU) Emissions Trading System (ETS), the question today is whether Member States and their grids can turn its revenues into connected, operating infrastructure at the pace the 2030 and 2050 targets demand.

Where the money comes from

The ETS, overseen by the European Commission’s Directorate-General for Climate Action (DG CLIMA), * requires heavy-emitting organisations, such as power generators, heavy industry, and aviation and maritime operators, to buy allowances for every tonne of carbon dioxide they emit. The total number of allowances is capped, and that limit falls over time, reducing total emissions and increasing the price for emitted carbon.

Some allowances are then auctioned, and the revenue generated is put to work delivering the bloc’s 2030 climate-related targets, such as reducing emissions by 55% compared to 1990 and increasing renewables to at least a 42% share of the final energy mix.

The ETS has been successful in generating vast sums to be invested in new renewables and grid upgrades. The Modernisation Fund is an example of this revenue-raising capability, channelling ETS funds toward lower-income Member States. But whatever the fund or initiative, putting the money to work requires mobilisation to overcome several challenges, including skills and supply-chain shortages.

Tackling the skills gap

People are the biggest constraint on deploying new transmission capacity. Skilled engineers are needed across the continent, particularly in those Member States that need to do most to build out their grids and incorporate more renewables.

However, skilled engineers move to where they are best rewarded. Given demand across the EU and other regions, this can drain capability from the places the Modernisation Fund is meant to support, as workers move to markets with better remuneration.

Addressing this requires capital, but not all of it should be upfront and just for infrastructure. Transmission and distribution system operators (TSOs and DSOs) need operating budgets large enough to develop staff, with funds deployed over many years. A ring-fenced operating allowance that TSOs and DSOs could draw on, to train, say, several thousand apprentices and graduates, with evidence that they are employed and developed in-country, would be a long-term fix for the skills crisis. Investing in people now is an investment in meeting the EU’s climate targets.

Supply chains squeezed

Grid build-out is also causing a shortage of equipment, including transformers, cables, and other assets. In a highly competitive market, those with the deepest pockets get first call, which can again price out utilities in constrained economies.

Part of the answer to the supply constraint must be manufacturing – at a basic level, we must increase supply. Incentives for locally based production would help, but this would be a long-term solution. A high-voltage cable factory can take roughly six years to build, so we must invest now with a view to carrying us beyond the 2030 targets.

Broader sourcing, similar to the flexibility allowed by the UK’s independent distribution network operator (IDNO) model, can address shorter-term needs. It means operators can buy beyond the traditional supplier base, widening the pool of available assets.

This could also make space for more network operators to deploy refurbished equipment. In the UK, many pre-used transformers are ready to be rebuilt and redeployed. There’s little reason to think EU Member States don’t have similar levels of reusable assets that could help relieve the asset squeeze on the grid build-out.

Applying funds to delivery

Ultimately, grid delivery is a condition for Europe’s carbon market to work as intended – heavy emitters can’t switch away from fossil fuels until there are grid-connected alternatives to switch to, and the grid can supply clean electricity at scale. Without that, there’s simply an increasing cost of carbon and nowhere to go. Climate policy and grid policy are therefore inseparable, and we must treat them as such.

We have been here before. The post-war build-out of Europe’s grid prompted a similar scramble for skills, equipment, and funding. Today’s rebuild of the power system exceeds that. The carbon price is doing its part by generating the needed funds. But the material factors constraining the effective discharge of ETS revenues need to be addressed too.