The Telangana High Court said Sem India Fab Pvt Ltd had proposed to invest about USD 2.2 billion, but apart from an unfinished skeletal shed, nothing had come up on the site.

Fab City row: Telangana HC brings in CBI over SBI’s Rs 500 cr loan

The High Court said the record showed a "hopeless and deplorable" state of affairs.

by · The Siasat Daily

Hyderabad: The Telangana High Court has, on its own, made the Central Bureau of Investigation (CBI) a party to a dispute over land allotted to Sem India Fab Pvt Ltd at Fab City in Raviryal, questioning how the State Bank of India (SBI) lent the company about Rs 500 crore after the state had already taken back most of the land.

Justice Nagesh Bheemapaka noted that SBI released the loan in 2011, while the government had resumed a large part of the land in February 2010. Given the facts on record, the judge said the court needed the assistance of the CBI’s Hyderabad unit.

The court said the record showed a “hopeless and deplorable” state of affairs, both in the company’s progress and in the checks the bank carried out before giving such a large loan.

The judge directed the registry to hand the CBI’s standing counsel the full set of petition papers and all related orders without delay, and posted the matter to December 4.

State Bank of India’s plea

The directions came on a writ petition filed by SBI. The bank has challenged the state government’s proceedings to resume 100 acre, spread over several survey numbers, at Fab City in Rangareddy district.

SBI also wanted the authorities stopped from interfering with its recovery action under the SARFAESI Act, which rests on a possession notice issued on September 12, 2012.

The bank said it lent the money relying on no-objection certificates (NOC) from the state government and Telangana Industrial Infrastructure Corporation Limited (TGIIC), which allowed the company to mortgage its leasehold rights. It said an equitable mortgage was created over the land as security.

At an earlier hearing in June, SBI’s counsel told the High Court that the principal amount was about Rs 169 crore, and that with interest the dues now exceed Rs 640 crore.

Telangana government’s stand

The state government contested SBI’s claim. It pointed out that the mortgage was created on August 20, 2011, about 18 months after the allotment had been cancelled.

It argued that title to the land always remained with the state through TGIIC. The NOCs, it said, did not pass any title or interest in the property to the company or to the SBI.

The High Court also referred to earlier findings that the company had made no real progress on its semiconductor project. The company had proposed to invest about USD 2.2 billion, but apart from an unfinished skeletal shed, nothing had come up on the site.

Long legal battle

The undivided Andhra Pradesh government allotted the 100 acre to the company on a 66-year lease in April 2007, at a rent of Rs 1 per acre a year. The state took back 78 acre in February 2010 under a government order, saying the project had not moved.

The resumption was earlier challenged in the High Court without success. When the SBI took the matter to the Supreme Court, the apex court declined to interfere.

In June this year, Justice Bheemapaka refused to stay the resumption for the time being. He also asked the SBI what action it had taken against the official who sanctioned the loan and why the bank was reluctant to seek a CBI investigation.

Fab City’s unfulfilled promise

Fab City was launched with great fanfare in 2006, when the Andhra Pradesh government and SemIndia, a consortium of non-resident Indian technologists, announced a USD 3 billion chip-making project on a 1,200-acre site near the new Hyderabad airport.

The project was meant to be India’s first semiconductor fabrication plant. It never took off, and by 2008 SemIndia had shelved its planned investment.