SINGAPORE: Passenger services on the Johor Bahru-Singapore Rapid Transit System (RTS) Link are now expected to begin in February 2027, with system tests and trial runs expected to be completed by the end of this year.

RTS Operations (RTSO), the operator of the cross-border rail service, announced the revised timeline on Friday (Oct 2).

“Taking into account the expected duration of works and the estimated duration required for safety certification from a third party and approval by both Grantors, passenger service is currently expected to commence in February 2027,” RTSO said.

It added that it expects all system tests and trial runs to be completed by Dec 31, 2026.

CNA Games

Guess Word
Crack the word, one row at a time

Buzzword
Create words using the given letters

Mini Sudoku
Tiny puzzle, mighty brain teaser

Mini Crossword
Small grid, big challenge

Word Search
Spot as many words as you can
Show More
Show Less

“Our goal is to provide a safe and reliable service on the RTS Link,” said RTSO, a joint venture between subsidiaries of Malaysia's Prasarana Malaysia Berhad and Singapore's SMRT Corporation.

The 4km rail link, which will connect Singapore’s Woodlands North Station to the Bukit Chagar Station in Johor Bahru, was initially expected to begin service at the end of 2026. 

Once operational, the cross-border rail service will have a peak capacity of up to 10,000 passengers per hour in each direction, with the journey between the two stations expected to take about five minutes.

Customs, immigration and quarantine facilities will be co-located at both stations, allowing passengers to clear immigration at their point of departure.

MISSED MILESTONES, PROJECT SUSPENSION

Plans for the RTS Link were first announced in 2010 as a joint project between Singapore and Malaysia.

The neighbours signed a legally binding agreement in January 2018, aiming to complete the project by Dec 31, 2024.

However, the original deadline was pushed back following several missed milestones and a suspension in April 2019 due to Malaysia requesting time to review the project.

Work on the RTS Link officially resumed in July 2020, with several key differences, including a change to the depot used on Malaysia's side. 

The rail link also shifted to a standalone Light Rail Transit system instead of leveraging Singapore's Thomson-East Coast Line MRT system as initially planned. 

The project completed its first test run in December 2025. In mid-August this year, Malaysian Transport Minister Anthony Loke said the station and rail infrastructure on his country’s side were completed, and the final testing phase was ongoing.

Authorities hope the new rail link will ease traffic conditions on the Causeway, which is one of the world's busiest border crossings.

It is also expected to have a significant impact on the economic front, shaping consumer spending, tourism flows and business competitiveness in the retail and F&B sectors.

A study commissioned by the Singapore Business Federation, Restaurant Association of Singapore and Singapore Retailers Association projected that Singapore residents would spend S$1.05 billion (US$810 million) more a year in Johor Bahru once the RTS Link opens.

Johor Bahru visitors, in comparison, are expected to spend S$756 million more in Singapore annually.

The study also projected a 51 per cent increase in outbound trips by Singapore consumers, adding 11.2 million Singapore-to-Johor Bahru round trips a year. 

Trips in the other direction are expected to grow by 3.3 million.

Source: CNA/rl

Newsletter

Morning Brief

Subscribe to CNA’s Morning Brief

An automated curation of our top stories to start your day.

Sign up for our newsletters

Get our pick of top stories and thought-provoking articles in your inbox

Subscribe here

Get the CNA app

Stay updated with notifications for breaking news and our best stories

Download here

Get WhatsApp alerts

Join our channel for the top reads for the day on your preferred chat app

Join here