The logo of copper miner Freeport-McMoRan Inc is displayed on their offices in Phoenix, Arizona, U.S. June 30, 2022. REUTERS/Ernest Scheyder

Freeport says Grasberg recovery not delayed until 2028, stands by 2027 forecast

· CNA · Join

Read a summary of this article on FAST.
Get bite-sized news via a new
cards interface. Give it a try.
Click here to return to FAST Tap here to return to FAST
FAST

May 11 : Freeport-McMoRan said on Monday that it still expects Indonesia's Grasberg copper and gold mine to resume full production by the end of 2027, reiterating a plan outlined last month and pushing back on reports that the restart could drag into 2028.

Grasberg, the world's second-largest copper mine and largest gold mine, was hit by a massive mud flow last September that killed seven workers and shuttered operations for nearly a month.

In late April, Freeport said recovery at the site was taking longer than expected and pushed back a forecast for 85 per cent of production to be restored by the second half of the year, saying that number would now be 65 per cent. Freeport's executives said that full operations would be restored by the end of 2027.

Last week, the Indonesian head of PT Freeport Indonesia, the company that owns the mine, said that the full production restart could be delayed further into 2028.

CNA Games

Guess Word
Crack the word, one row at a time

Buzzword
Create words using the given letters

Mini Sudoku
Tiny puzzle, mighty brain teaser

Mini Crossword
Small grid, big challenge

Word Search
Spot as many words as you can
Show More
Show Less

That news sent copper prices to a three-month high as markets absorbed what seemed like yet another supply shock amid surging demand for the red metal.

PT Freeport Indonesia is majority controlled by Indonesian government entities that hold a 51.24 per cent stake to Freeport's 48.76 per cent. Phoenix-based Freeport manages Grasberg's operations.

"PT Freeport Indonesia's ramp-up progress and revised mine plans were disclosed on April 23 in connection with Freeport's earnings release," Freeport said in an emailed statement to Reuters. "Media headlines are misleading as this information was publicly disclosed more than two weeks ago."

When asked about the discrepancy in statements between Freeport's headquarters in Phoenix and the operations in Indonesia, a Freeport spokesperson said that if there were an additional delay, the company would have alerted markets.

Freeport filed a quarterly update with U.S. regulators on Friday that reiterated the 2027 timeline.

Freeport CEO Kathleen Quirk plans to discuss the Grasberg operations on Tuesday during the Bank of America Global Metals, Mining and Steel Conference, the company said.

Freeport's shares gained 5 per cent on Monday to $64.75 as copper prices gained more than 2.5 per cent.

Source: Reuters

Newsletter

Week in Review

Subscribe to our Chief Editor’s Week in Review

Our chief editor shares analysis and picks of the week's biggest news every Saturday.

Sign up for our newsletters

Get our pick of top stories and thought-provoking articles in your inbox

Subscribe here

Get the CNA app

Stay updated with notifications for breaking news and our best stories

Download here

Get WhatsApp alerts

Join our channel for the top reads for the day on your preferred chat app

Join here