Aidel: Serian-Gedong-Samarahan dual carriageway project includes provisions for future ART route, utility corridors
KUCHING (April 8): The Serian-Gedong-Samarahan dual carriageway project is progressing ahead of schedule, with physical works currently at 7.77 per cent completion. A Sarawak Public Communication Unit (Ukas) report quoted Deputy Minister of Infrastructure and Port Development Datuk Aidel Lariwoo as saying the project is 4.31 per cent ahead of its scheduled progress of 3.46Read More
8 Apr 07:38 · Borneo Post Online