Radar hurdles, engine delays and missed deadlines put HAL’s January 2027 Tejas Mk1A delivery target to the test
HAL's delivery record raises further concerns. The final two Tejas Mk1 trainers, ordered in 2010 and originally due by December 2016, were handed over only in September 2026. Although the Mk1 and Mk1A are different programmes, the prolonged delays underline why HAL's latest commitments must be judged against actual deliveries rather than revised timelines.